Skip to main content

NEWBeamery Field Report: The Crib

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

As the NEWBeamery project progresses past the footer and concrete slab phase, our team has begun the framing and wall assembly process.

During this phase of the project glulam timber posts are anchored to the concrete footers, and then surrounded with panelized wall sections, forming what we affectionately refer to as “the crib” because it resembles an oversized baby’s crib.

Next up we will be flying the trusses and assembling our roof system.

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility

 

New Energy Works NEWBeamery, the new timber frame and glulam production facility


 

See more about the NEWBeamery:

NEWBeamery Update: Breaking Ground in McMinnville, OR | New Energy Works

NEWBeamery Update: Responsible Concrete Slab Pour | New Energy Works

Partner shout out for this phase: Prime Contracting